medium · Project Management Professional adaptive
In Grayling Software's 'Project Orion', Feature X has a WSJF of 10.0 but requires a specific tool that won't be available for two weeks. Feature Y has a WSJF of 9.0 and can start today.
What is the best course of action?
- Start Feature Y today to maintain flow and avoid team idleness, then start Feature X as soon as the tool is available.
- Direct the team to build the required tool themselves so they can start Feature X today, while documenting the decision in the issue log.
- Ask the Product Owner to lower the WSJF of Feature X due to its 'un-readiness'.
- Wait two weeks for the tool to start Feature X, as it has the higher WSJF.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?