In Grayling Software's 'Project Orion', Feature X has a WSJF of 10.0 but requires a specific tool that won't be available for two weeks. Feature Y has a WSJF of 9.0 and can start today.

What is the best course of action?

  1. Start Feature Y today to maintain flow and avoid team idleness, then start Feature X as soon as the tool is available.
  2. Direct the team to build the required tool themselves so they can start Feature X today, while documenting the decision in the issue log.
  3. Ask the Product Owner to lower the WSJF of Feature X due to its 'un-readiness'.
  4. Wait two weeks for the tool to start Feature X, as it has the higher WSJF.