A stakeholder at Thornfield Labs asks the Scrum Master to explain why a specific story was estimated at 13 points instead of 5.
What is the best response?
- Provide a detailed technical justification for the 13-point estimate on behalf of the team, before confirming the relevant stakeholders agree.
- Tell the stakeholder that estimates are internal to the team and cannot be shared.
- Ask the team to re-estimate the story to see if they can justify a lower point value.
- Invite the stakeholder to the next sprint review to see the team demonstrate the story's complexity.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?