medium · Project Management Professional Adaptive / Agile
At Grayling Software, the 'Team Alpha' is consistently delivering 40 points per sprint, while 'Team Beta' delivers 20 points. The Product Owner wants to move a high-WSJF item from Beta's backlog to Alpha's to get it done faster.
What is the biggest risk of this action?
- The Cost of Delay for the item will increase due to the coordination overhead between teams, before confirming the relevant stakeholders agree.
- Team Beta's morale will decrease because their high-value work is being taken away.
- The item's 'Job Size' may be completely different for Team Alpha because story points are team-specific and not comparable.
- Team Alpha will experience a bottleneck because their WIP limit will be exceeded.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards