medium · Project Management Professional adaptive

At Grayling Software, the 'Team Alpha' is consistently delivering 40 points per sprint, while 'Team Beta' delivers 20 points. The Product Owner wants to move a high-WSJF item from Beta's backlog to Alpha's to get it done faster.

What is the biggest risk of this action?

  1. The Cost of Delay for the item will increase due to the coordination overhead between teams, before confirming the relevant stakeholders agree.
  2. Team Beta's morale will decrease because their high-value work is being taken away.
  3. The item's 'Job Size' may be completely different for Team Alpha because story points are team-specific and not comparable.
  4. Team Alpha will experience a bottleneck because their WIP limit will be exceeded.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials