KomFi. Academy

medium · Project Management Professional Adaptive / Agile

At Grayling Software, the 'Team Alpha' is consistently delivering 40 points per sprint, while 'Team Beta' delivers 20 points. The Product Owner wants to move a high-WSJF item from Beta's backlog to Alpha's to get it done faster.

What is the biggest risk of this action?

  1. The Cost of Delay for the item will increase due to the coordination overhead between teams, before confirming the relevant stakeholders agree.
  2. Team Beta's morale will decrease because their high-value work is being taken away.
  3. The item's 'Job Size' may be completely different for Team Alpha because story points are team-specific and not comparable.
  4. Team Alpha will experience a bottleneck because their WIP limit will be exceeded.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards