hard · Project Management Professional Adaptive / Agile

Northwick Clinics is transitioning its patient record system using a hybrid approach. The data migration workstream follows a predictive baseline while the user interface team uses two-week iterations. A recent audit reveals that the predictive workstream is currently at PV = $450,000, EV = $380,000, and AC = $410,000.

What is the cost performance of this workstream and what does it indicate?

  1. The CPI is 1.08, indicating high efficiency in the data migration workstream.
  2. The SPI is 0.84, indicating the workstream is currently ahead of schedule.
  3. The CV is -$30,000, indicating a favorable cost variance for the clinician team.
  4. The CPI is 0.93, indicating the workstream is currently over budget.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards