easy · Project Management Professional Adaptive / Agile

A project manager at Driftwood Health is managing a hybrid project. The software team is blocked because the hardware team, using a predictive approach, is late with a delivery.

What is the first action?

  1. Submit a change request to the CCB for the software team's delay.
  2. Facilitate a meeting between both teams to coordinate a resolution.
  3. Escalate the hardware team's performance to the department head.
  4. Tell the hardware team they must follow the software team's sprint schedule.