KomFi. Academy

hard · Project Management Professional Adaptive / Agile

At Nimbus Clinics, a geopolitical shift has led to an 'Issue.' A risk that was identified in the register has now occurred.

What is the first thing the project manager should do?

  1. Inform the sponsor that a new problem has arisen and ask for guidance.
  2. Re-perform qualitative risk analysis on the event.
  3. Execute the planned risk response and update the issue log.
  4. Create a new risk register entry for the occurring event.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards