medium · Project Management Professional adaptive

Thornfield Labs has a team with an average velocity of 25 points. The Product Backlog contains 200 points of work. A new regulatory requirement adds 50 points to the backlog.

What is the most accurate forecast for the remaining duration?

  1. Ask the sponsor for more funding to reduce the number of iterations to 6.
  2. Exactly 10 iterations, and update the schedule baseline to reflect this fixed date.
  3. 10 iterations, acknowledging that velocity ranges may vary.
  4. 8 iterations, assuming the team will increase efficiency to accommodate the new work.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials