medium · Project Management Professional adaptive
Thornfield Labs has a team with an average velocity of 25 points. The Product Backlog contains 200 points of work. A new regulatory requirement adds 50 points to the backlog.
What is the most accurate forecast for the remaining duration?
- Ask the sponsor for more funding to reduce the number of iterations to 6.
- Exactly 10 iterations, and update the schedule baseline to reflect this fixed date.
- 10 iterations, acknowledging that velocity ranges may vary.
- 8 iterations, assuming the team will increase efficiency to accommodate the new work.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?