Thornfield Labs has a team with an average velocity of 25 points. The Product Backlog contains 200 points of work. A new regulatory requirement adds 50 points to the backlog.

What is the most accurate forecast for the remaining duration?

  1. Ask the sponsor for more funding to reduce the number of iterations to 6.
  2. Exactly 10 iterations, and update the schedule baseline to reflect this fixed date.
  3. 10 iterations, acknowledging that velocity ranges may vary.
  4. 8 iterations, assuming the team will increase efficiency to accommodate the new work.