hard · Project Management Professional adaptive
Amberline Transit is utilizing an adaptive approach for its new signaling system. The team's historical velocity is 40 points per sprint. For the upcoming sprint, two senior developers will be on leave for 5 days each in a 10-day sprint, and the team must attend 8 hours of mandatory training.
What is the most appropriate action for the project manager to take during sprint planning?
- Ask the Product Owner to approve a 'Definition of Done' waiver for this sprint only.
- Collaborate with the team to calculate the reduced sprint capacity and pull work accordingly.
- Ensure the team commits to 40 points to maintain the historical velocity trend.
- Request the functional manager to provide temporary contractors to cover the 10 days of leave.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?