hard · Project Management Professional adaptive

Amberline Transit is utilizing an adaptive approach for its new signaling system. The team's historical velocity is 40 points per sprint. For the upcoming sprint, two senior developers will be on leave for 5 days each in a 10-day sprint, and the team must attend 8 hours of mandatory training.

What is the most appropriate action for the project manager to take during sprint planning?

  1. Ask the Product Owner to approve a 'Definition of Done' waiver for this sprint only.
  2. Collaborate with the team to calculate the reduced sprint capacity and pull work accordingly.
  3. Ensure the team commits to 40 points to maintain the historical velocity trend.
  4. Request the functional manager to provide temporary contractors to cover the 10 days of leave.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials