hard · Project Management Professional adaptive
Glassford Municipal is implementing a new digital voting system. The project is 70% complete when the city council introduces a new accessibility regulation that will require 15 new features. The project manager determines that these features will cost an additional $200,000 and delay the launch by two months.
What is the most appropriate action for the project manager?
- Reject the request because the project is too far along and the budget is already fixed.
- Incorporate the new features immediately to ensure the project remains compliant with the law.
- Inform the city council that the project will be delivered as originally scoped to avoid a delay.
- Perform an impact analysis and present the findings to the Change Control Board for a decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?