hard · Project Management Professional Adaptive / Agile
Glassford Municipal is implementing a new digital voting system. The project is 70% complete when the city council introduces a new accessibility regulation that will require 15 new features. The project manager determines that these features will cost an additional $200,000 and delay the launch by two months.
What is the most appropriate action for the project manager?
- Reject the request because the project is too far along and the budget is already fixed.
- Incorporate the new features immediately to ensure the project remains compliant with the law.
- Inform the city council that the project will be delivered as originally scoped to avoid a delay.
- Perform an impact analysis and present the findings to the Change Control Board for a decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards