medium · Project Management Professional adaptive

During a project at Cinderwell Water, two senior engineers are in a technical deadlock regarding the pump design. The disagreement is starting to delay the procurement schedule.

What is the most appropriate action?

  1. Escalate the technical decision to the Chief Engineer to break the deadlock. given the information provided
  2. Apply the 'Force' mode and choose a design to ensure the schedule is maintained.
  3. Facilitate a collaborative session to surface interests and find a technically sound compromise.
  4. Select the design that is most likely to meet the original budget to avoid a cost variance.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials