A team at Quill Digital is suffering from high cycle times. The PM observes that the team frequently ignores WIP limits to handle 'urgent' maintenance tasks.
What is the most effective way to address this systemic issue?
- Report the team members to their functional managers for process non-compliance.
- Double the WIP limits to accommodate both maintenance and features.
- Instruct the product owner to stop accepting maintenance requests during the sprint, after reviewing the current risk register entries.
- Establish a dedicated 'swimlane' for maintenance with its own separate WIP limit to prevent it from overwhelming the planned work.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?