Northwick Clinics is transitioning a health records project to an adaptive approach. The project manager identifies that the 'Verification' band on the CFD has been flat for two weeks while the 'Development' band continues to grow.

What is the most likely cause of this pattern?

  1. A critical blocker is preventing work from moving out of the development stage into verification.
  2. The team has successfully implemented a vertical slicing strategy for all user stories.
  3. The product owner has recently reprioritized the backlog to favor high-value items. given the information provided
  4. The project has reached its natural conclusion and the team is entering the 'Adjourning' phase.