At Cinderwell Water, a project manager is using a Responsibility Assignment Matrix (RACI). They notice that one activity has three people marked as 'Accountable'.

What is the most likely problem?

  1. The project manager should change two of the 'A's to 'R's to solve the problem.
  2. This indicates that the activity is too complex and should be decomposed.
  3. This is acceptable as long as all three people agree on the decisions.
  4. This creates a risk that nobody will take final ownership of the outcome.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials