medium · Project Management Professional adaptive
At Cinderwell Water, a project manager is using a Responsibility Assignment Matrix (RACI). They notice that one activity has three people marked as 'Accountable'.
What is the most likely problem?
- The project manager should change two of the 'A's to 'R's to solve the problem.
- This indicates that the activity is too complex and should be decomposed.
- This is acceptable as long as all three people agree on the decisions.
- This creates a risk that nobody will take final ownership of the outcome.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?