medium · Project Management Professional adaptive

A Trestle Ports team is building a logistics tracker. Mid-PI, they discover a critical security vulnerability that requires an immediate technical pivot. This pivot makes the current 'PI Objectives' impossible to meet.

What is the PM's priority?

  1. Request a 'Scope Waiver' from the Trestle Ports security officer so the project can proceed as planned.
  2. Instruct the team to work nights and weekends to both fix the vulnerability and meet the original PI objectives.
  3. Immediately communicate the 'Security Risk' to governance and facilitate a reprioritization of the PI backlog to address the threat.
  4. Document the vulnerability in the 'Watch List' and finish the current PI objectives to maintain stakeholder trust, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials