A project at Kestrel Civic is using a Fixed Price Incentive Fee (FPIF) contract. The Target Cost is 500,000, Target Profit is 50,000, Ceiling Price is 600,000, and the Share Ratio is 80/20.
What is the Point of Total Assumption (PTA)?
- 550,000
- 600,000
- 512,500
- 562,500