At Dovetail Clinics, a Product Owner is consistently adding items to the current sprint backlog mid-iteration. The team's velocity has dropped by 25% as a result.

What is the project manager's best response?

  1. Ask the team to work overtime to accommodate the Product Owner's urgent requests.
  2. Report the drop in velocity as a team performance issue in the status report.
  3. Coach the Product Owner on the importance of protecting the sprint commitment.
  4. Resign from the project as the Product Owner is violating the core Scrum rules.