Ironvale Grid is managing a utility upgrade. A critical 'Risk Reduction' item (CoD = 80, Size = 10) is identified during a sprint. The Product Owner is reluctant to prioritize it over 'Customer UI' (CoD = 40, Size = 5).
What is the project manager’s best response?
- Facilitate a discussion on WSJF, highlighting that the Risk Reduction item (8.0) has a higher value density than the UI (8.0) when accounting for opportunity enablement.
- Direct the team to work on the Risk Reduction item because security and risk override customer features, while documenting the decision in the issue log, after reviewing the current risk register entries.
- Submit a change request to the CCB to mandate the risk item be completed in the next sprint.
- Escalate the PO's reluctance to the Chief Information Security Officer (CISO).
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?