easy · Project Management Professional Adaptive / Agile
At Thornfield Labs, a Product Owner wants to add a 13-point story to the middle of an active sprint.
What is the Scrum Master's role?
- Refuse the request and tell the Product Owner to wait for the next sprint, before confirming the relevant stakeholders agree.
- Escalate the Product Owner's lack of process discipline to the PMO.
- Facilitate a discussion about the impact on the sprint goal and help the team and PO decide if it fits.
- Add the story to the sprint backlog and tell the team they must finish it.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards