medium · Project Management Professional adaptive
Osprey Bank's mobile app team has a backlog of 20 features. The Product Owner wants to release a version of the app that allows users to deposit checks via their camera, as this is the most requested capability that will drive adoption.
What is this release version called?
- Technical Proof of Concept
- Minimum Viable Product
- Validated Learning Increment
- Minimum Marketable Feature
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?