Trestle Ports is using a Kanban system. The 'Testing' state has a WIP limit of 3, but there are 5 items currently in that column. Stakeholders are complaining about a slowdown.

What should the PM facilitate?

  1. A 'Stop Starting, Start Finishing' session where developers help the testers clear the bottleneck before pulling new work.
  2. Assigning two developers to permanently move into the testing team to handle the volume.
  3. Increasing the WIP limit to 6 to accommodate the extra items and reduce stakeholder complaints, after reviewing the current risk register entries.
  4. Filing a quality report showing that the testers are underperforming against the baseline.