hard · Project Management Professional adaptive
Trestle Ports is using a Kanban system. The 'Testing' state has a WIP limit of 3, but there are 5 items currently in that column. Stakeholders are complaining about a slowdown.
What should the PM facilitate?
- A 'Stop Starting, Start Finishing' session where developers help the testers clear the bottleneck before pulling new work.
- Assigning two developers to permanently move into the testing team to handle the volume.
- Increasing the WIP limit to 6 to accommodate the extra items and reduce stakeholder complaints, after reviewing the current risk register entries.
- Filing a quality report showing that the testers are underperforming against the baseline.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?