medium · Project Management Professional adaptive

A Nimbus Clinics project manager is using 'Little's Law' (Cycle Time = WIP / Throughput) to show the team that their 'Shared Vision' is being compromised by multitasking across 15 different features.

What should the PM recommend?

  1. Implement a 'WIP Limit' on the Kanban board to force focus on finishing fewer features that directly align with the highest-priority OKR.
  2. Hide five of the features in a 'Parking Lot' so the WIP appears lower on the stakeholder dashboard.
  3. Tell the team to work faster (increase Throughput) so the high WIP doesn't affect their Cycle Time.
  4. Add three more developers to the team so they can handle all 15 features simultaneously without increasing cycle time, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials