easy · Project Management Professional adaptive
A Product Owner at Whitlock Software is using 'MoSCoW' to prioritize the 'Clinic App' backlog. A stakeholder insists that a 'Delighter' feature be a 'Must-Have.'
What should the project manager do?
- Automatically change the feature to 'Must-Have' to maintain good stakeholder relations.
- Escalate the stakeholder's request to the steering committee for a final ruling.
- Suggest moving a different 'Must-Have' feature to 'Won't-Have' to maintain the sprint capacity, after reviewing the current risk register entries.
- Facilitate a discussion to clarify the 'Must-Have' criteria (e.g., project fails without it) and support the Product Owner's final decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?