easy · Project Management Professional Adaptive / Agile
A Product Owner at Whitlock Software is using 'MoSCoW' to prioritize the 'Clinic App' backlog. A stakeholder insists that a 'Delighter' feature be a 'Must-Have.'
What should the project manager do?
- Automatically change the feature to 'Must-Have' to maintain good stakeholder relations.
- Escalate the stakeholder's request to the steering committee for a final ruling.
- Suggest moving a different 'Must-Have' feature to 'Won't-Have' to maintain the sprint capacity, after reviewing the current risk register entries.
- Facilitate a discussion to clarify the 'Must-Have' criteria (e.g., project fails without it) and support the Product Owner's final decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards