medium · Project Management Professional adaptive
Fenwick Grid is building a grid-management tool. The team's Objective is "Eliminate critical safety incidents through better data visualization." During the retrospective, the project manager notices that while no incidents occurred, the team feels they have failed because they only completed 70% of the stories in the sprint.
What should the project manager do?
- Implement a forced ranking system to identify which team members are responsible for the unfinished work.
- Ask the Product Owner to remove the incomplete stories from the backlog to make the sprint 'appear' successful.
- Coach the team on how to improve their estimation so they can achieve 100% completion in the next sprint.
- Remind the team that their success is measured by the outcome (zero incidents) rather than plan conformance.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?