hard · Project Management Professional Adaptive / Agile
At Grayling Software, a developer identifies a technical solution that would make a feature run twice as fast as required, but it will take two extra days of work. The project is currently on schedule.
What should the project manager do?
- Allow the developer to proceed if they can finish the work within the current sprint.
- Submit a change request to the CCB to incorporate the faster solution.
- Direct the developer to follow the approved requirements and acceptance criteria.
- Approve the solution because it provides significant extra value to the customer.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards