KomFi. Academy

hard · Project Management Professional Adaptive / Agile

At Grayling Software, a developer identifies a technical solution that would make a feature run twice as fast as required, but it will take two extra days of work. The project is currently on schedule.

What should the project manager do?

  1. Allow the developer to proceed if they can finish the work within the current sprint.
  2. Submit a change request to the CCB to incorporate the faster solution.
  3. Direct the developer to follow the approved requirements and acceptance criteria.
  4. Approve the solution because it provides significant extra value to the customer.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards