hard · Project Management Professional adaptive
Fenwick Grid observes that the 'Arrival' curve and 'Done' curve on their CFD are perfectly parallel, but the vertical distance between them is very large (WIP = 40). The team is busy but stakeholders say it takes 'months' to get a feature.
What should the project manager do?
- Facilitate a team agreement to drastically reduce WIP limits to shorten the lead time.
- Escalate to the Product Owner that the team is overloaded and needs a 'sprint holiday.'
- Celebrate the stability of the system and maintain the current WIP limits.
- Assign specific 'due dates' to each item in the WIP to force faster completion.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?