Fenwick Grid observes that the 'Arrival' curve and 'Done' curve on their CFD are perfectly parallel, but the vertical distance between them is very large (WIP = 40). The team is busy but stakeholders say it takes 'months' to get a feature.

What should the project manager do?

  1. Facilitate a team agreement to drastically reduce WIP limits to shorten the lead time.
  2. Escalate to the Product Owner that the team is overloaded and needs a 'sprint holiday.'
  3. Celebrate the stability of the system and maintain the current WIP limits.
  4. Assign specific 'due dates' to each item in the WIP to force faster completion.