Fenwick Grid observes that the 'Arrival' curve and 'Done' curve on their CFD are perfectly parallel, but the vertical distance between them is very large (WIP = 40). The team is busy but stakeholders say it takes 'months' to get a feature.

What should the project manager do?

  1. Facilitate a team agreement to drastically reduce WIP limits to shorten the lead time.
  2. Escalate to the Product Owner that the team is overloaded and needs a 'sprint holiday.'
  3. Celebrate the stability of the system and maintain the current WIP limits.
  4. Assign specific 'due dates' to each item in the WIP to force faster completion.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials