easy · Project Management Professional adaptive

At Whitlock Software, a team developing a new API suite realizes mid-sprint that the 'Needs' section of the Product Vision Board does not align with recently gathered developer feedback. The team requests an immediate rewrite of the vision.

What should the project manager do first?

  1. Update the Product Vision Board immediately to reflect the team's new understanding of the user needs, before confirming the relevant stakeholders agree.
  2. Facilitate a session with the team and Product Owner to understand the specific gaps in the current vision.
  3. Submit a formal change request to the Change Control Board (CCB) to modify the project scope baseline.
  4. Escalate the team's concerns to the Executive Sponsor to seek guidance on the strategic direction.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials