Driftwood Health is transitioning its patient portal to a new vendor. The project is at the 80% completion mark, but the business case for the transition has recently expired because of a shift in national health data policy.
What should the project manager do first?
- Update the project plan to incorporate the new health data policy requirements.
- Submit the findings to project governance for a go/no-go decision against the updated policy.
- Cancel the project immediately and release the team to other initiatives. given the information provided
- Finish the remaining 20% of the work to avoid wasting the resources already spent.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?