hard · Project Management Professional adaptive

A team at Marrowfield Labs has a velocity that fluctuates between 15 and 45 points per sprint. The Director is frustrated with the lack of predictability.

What should the project manager do first?

  1. Escalate the predictability issue to the Product Owner and suggest they prioritize easier stories to stabilize the velocity.
  2. Instruct the team to use hours instead of story points to provide more granular and predictable data for the Director.
  3. Acknowledge the Director's frustration and promise that the team will maintain a spoint average starting next sprint. given the information provided
  4. Review the team's Definition of Ready and backlog refinement process to ensure stories are properly sized and understood before the sprint.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials