A new developer at Dovetail Clinics is struggling to complete her assigned stories. The other team members are beginning to complain about her performance.

What should the project manager do first?

  1. Meet with the developer privately to understand if the issue is a skill gap, a will issue, or an environmental blocker.
  2. Assign a senior developer to take over her tasks for the remainder of the sprint.
  3. Discuss the performance issues during the next Daily Scrum to get the team's feedback, after reviewing the current risk register entries.
  4. Notify the developer's functional manager that she is not a good fit for the project.