A new developer at Dovetail Clinics is struggling to complete her assigned stories. The other team members are beginning to complain about her performance.
What should the project manager do first?
- Meet with the developer privately to understand if the issue is a skill gap, a will issue, or an environmental blocker.
- Assign a senior developer to take over her tasks for the remainder of the sprint.
- Discuss the performance issues during the next Daily Scrum to get the team's feedback, after reviewing the current risk register entries.
- Notify the developer's functional manager that she is not a good fit for the project.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?