A project manager at Northwick Clinics is informed mid-project that a new data privacy regulation will take effect in six months. The project's current release plan does not include the required security controls.
What should the project manager do first?
- Instruct the solution architect and the team to analyze the gap between current state and the new regulation.
- Continue with the current plan and address the regulation as part of a follow-up maintenance project.
- Notify the project sponsor that the release date will need to be pushed back by two months.
- Submit a change request to the CCB to add the new security controls to the scope baseline. given the information provided
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?