medium · Project Management Professional adaptive
Sable Civic is developing a community portal using an adaptive approach. Feature Alpha has a WSJF score of 12.5 and Feature Beta has a WSJF score of 8.2. Feature Gamma has a WSJF score of 5.1 but is required by a new municipal safety regulation effective in 12 weeks. Velocity data suggests that Alpha and Beta together will take 11 weeks.
What should the project manager do first?
- Instruct the Product Owner to prioritize Alpha and Beta to maximize value delivery per unit of effort.
- Escalate the conflict between the WSJF scores and the regulatory date to the municipal steering committee.
- Reject the regulatory change request because it disrupts the team's planned value delivery for the current release.
- Meet with the Product Owner to ensure Feature Gamma is prioritized to meet the 12-week regulatory deadline.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?