medium · Project Management Professional adaptive
A project manager at Glassford Municipal discovers that the project's 'actual cost' is being reported incorrectly due to a system error. The error makes the project look significantly under budget.
What should the project manager do?
- Correct the reporting immediately and inform the sponsor of the discrepancy.
- Use the error as an opportunity to secure more contingency reserve.
- Wait until the system is fixed before providing a corrected report.
- Document the system error in the issue log and continue using the current reports.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?