A project manager at Glassford Municipal discovers that the project's 'actual cost' is being reported incorrectly due to a system error. The error makes the project look significantly under budget.

What should the project manager do?

  1. Correct the reporting immediately and inform the sponsor of the discrepancy.
  2. Use the error as an opportunity to secure more contingency reserve.
  3. Wait until the system is fixed before providing a corrected report.
  4. Document the system error in the issue log and continue using the current reports.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials