hard · Project Management Professional adaptive

Amberline Transit's developers have identified a major technical risk that could impact the product goal. The Product Owner is absent and has not responded to the team's alerts for three days.

What should the project manager do next?

  1. Instruct the developers to implement a technical fix for the risk immediately to protect the project.
  2. Escalate the risk directly to the project sponsor and request that the project be paused. given the information provided
  3. Update the risk register with the details and wait for the PO to respond to the next scheduled update.
  4. Communicate the risk and its potential impact to the PO and their manager, requesting an urgent decision.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials