hard · Project Management Professional adaptive
Amberline Transit's developers have identified a major technical risk that could impact the product goal. The Product Owner is absent and has not responded to the team's alerts for three days.
What should the project manager do next?
- Instruct the developers to implement a technical fix for the risk immediately to protect the project.
- Escalate the risk directly to the project sponsor and request that the project be paused. given the information provided
- Update the risk register with the details and wait for the PO to respond to the next scheduled update.
- Communicate the risk and its potential impact to the PO and their manager, requesting an urgent decision.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?