Glassford Municipal is upgrading its water treatment software using a predictive approach. During a status meeting, a team member reports that a critical task is five days behind. The project manager identifies that this task has ten days of total float.
What should the project manager do next?
- Update the schedule model to reflect the current status and monitor the remaining float.
- Escalate the delay to the project sponsor as a threat to the project baseline.
- Authorize overtime for the team to recover the five-day delay immediately.
- Submit a change request to extend the project finish date by five days. given the information provided
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?