Dovetail Clinics is implementing a patient-scheduling AI. The business case assumes a 20% reduction in 'no-shows.' After three months, the system is 95% accurate, but no-shows have only decreased by 2%.

What should the project manager do next?

  1. Investigate the operational reasons why the technical accuracy is not translating into the expected benefit.
  2. Update the benefits management plan to reflect the new 2% reality as the baseline for the future, while documenting the decision in the issue log.
  3. Instruct the developers to increase the AI model's accuracy to 99% to improve the results.
  4. Continue with the planned rollout since the technical performance meets the agreed requirements.

Sign up free to see the explanation and track your rank →

More Project Management Professional Adaptive / Agile practice

All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards