hard · Project Management Professional adaptive

The Director of Peakstone Rail is unhappy that the adaptive team is 'only' delivering 20 points per sprint when the business case was built on an assumption of 40 points per sprint.

What should the project manager do next?

  1. Ask the Product Owner to remove the 50 % least valuable items from the backlog so the project can still finish on the original target date.
  2. Perform an analysis of the business case validity given the observed velocity and present the findings to the Sponsor for a strategic decision.
  3. Submit a change request to the Change Control Board to update the project charter with the new, lower velocity target. given the information provided
  4. Convene a mandatory retrospective to find ways for the team to double their velocity to align with the business case assumptions.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials