hard · Project Management Professional adaptive
During a sprint for Amberline Transit's fare-card upgrade, the Product Owner is pulled into an emergency meeting regarding a city council budget hearing. Several developers are blocked because the PO has not yet signed off on three completed stories.
What should the project manager do next?
- Collaborate with the team to identify items that can be progressed while waiting for the PO to return.
- Request that the fare-card department head provide a temporary backup PO to review the stories immediately.
- Accept the completed stories on behalf of the PO so the team can maintain their current velocity.
- Log the PO absence as a high-priority risk in the risk register and continue monitoring the situation.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?