hard · Project Management Professional Adaptive / Agile

At Solstice Labs, the PO is also a Senior VP and their absence is due to 'competing priorities'. The project is falling behind.

What should the project manager recommend to the Lab's leadership?

  1. The project should be converted to a predictive approach so the PO only needs to attend monthly gates.
  2. The team should be given 'Unlimited Overtime' to catch up on the work they missed during the PO's absence.
  3. The PO should be replaced by someone who has the dedicated 'Time and Capacity' to perform the role daily.
  4. The Project Manager should take over the PO role and the Lab should hire a new Scrum Master.

Sign up free to see the explanation and track your rank →