hard · Project Management Professional adaptive
Redcedar Energy is manages a smart-metering project. A stakeholder complains that their request is taking 'forever' despite being approved weeks ago. The CFD shows parallel bands with a 20-item gap in 'Backlog' and a 30-item gap in 'Dev'. Throughput is 5 per week.
What should the project manager say?
- Promise the stakeholder that their request will be prioritized for the very next iteration.
- Blame the development team for the long lead times and promise to investigate their productivity.
- Explain that the current system lead time is approximately 10 weeks and discuss the current WIP levels.
- Advise the stakeholder to submit a new, higher-priority request to jump the current queue. given the information provided
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?