During a sprint at Thornfield Labs, a developer realizes a story estimated at 3 points is actually a 13.

What should the Scrum Master do?

  1. Change the estimate in the system to 13 points so the velocity report is accurate.
  2. Tell the developer to work overtime to finish the 13 points within the 3-point budget.
  3. Facilitate a discussion with the Product Owner about the impact on the sprint goal.
  4. Instruct the developer to move the story back to the product backlog immediately.