easy · Project Management Professional Adaptive / Agile
During a sprint at Thornfield Labs, a developer realizes a story estimated at 3 points is actually a 13.
What should the Scrum Master do?
- Change the estimate in the system to 13 points so the velocity report is accurate.
- Tell the developer to work overtime to finish the 13 points within the 3-point budget.
- Facilitate a discussion with the Product Owner about the impact on the sprint goal.
- Instruct the developer to move the story back to the product backlog immediately.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards