easy · Project Management Professional adaptive
Thornfield Labs is transitionining from predictive to adaptive. The team is worried that story points aren't as 'accurate' as hour-based estimates.
What should the Scrum Master do?
- Facilitate a workshop using historical data to show how relative sizing tracks with actual delivery speed.
- Mandate the use of story points and explain that accuracy will improve over time.
- Tell the team that 'accuracy' is less important than 'velocity' in adaptive projects.
- Allow the team to track both hours and points for the next six months to compare them, without revisiting the agreed prioritization criteria.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?