medium · Project Management Professional adaptive

Coveport Logistics is using Kanban for its supply chain dashboard. The board shows a Cumulative Flow Diagram (CFD) where the 'Testing' band is steadily widening, while the 'Done' band is flat. Team members are starting new 'Development' tasks.

What should the servant leader do first?

  1. Update the project schedule baseline to reflect the delay in the 'Done' deliverables and inform the sponsor.
  2. Implement a lower Work in Progress (WIP) limit for the 'Development' column and ask developers to help with testing.
  3. Direct the developers to continue their work but spend the last hour of every day on testing activities.
  4. Increase the velocity of the testing team by adding two more quality assurance specialists from another project, without revisiting the agreed prioritization criteria.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials