At Thornfield Labs, the team's velocity has been exactly 35 points for four sprints. The Scrum Master suspects the team is 'parking' work to hit this number.
What should the SM do first?
- Notify the Product Owner that the team is potentially manipulating their delivery data, before confirming the relevant stakeholders agree.
- Challenge the team during planning to take on 45 points to break the pattern.
- Facilitate a blameless discussion in the retrospective about how velocity is being used and perceived.
- Secretly audit the story points of completed work to find evidence of 'parking'.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?