easy · Project Management Professional adaptive
Quayport Logistics is using a Kanban board for their delivery process. They have a work-in-progress (WIP) limit of 5 items in the 'Testing' column, which is currently full. A new item is ready for testing.
What should the team do?
- Ignore the WIP limit this one time because the new item is a high-priority request from the sponsor.
- Wait to move the new item into 'Testing' until one of the current five items is completed and moved out.
- Temporarily increase the WIP limit to 6 so the team can maintain their current pace of development.
- Ask the project manager to reassign two developers to the 'Testing' team to clear the backlog. given the information provided
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?