easy · Project Management Professional adaptive

Quayport Logistics is using a Kanban board for their delivery process. They have a work-in-progress (WIP) limit of 5 items in the 'Testing' column, which is currently full. A new item is ready for testing.

What should the team do?

  1. Ignore the WIP limit this one time because the new item is a high-priority request from the sponsor.
  2. Wait to move the new item into 'Testing' until one of the current five items is completed and moved out.
  3. Temporarily increase the WIP limit to 6 so the team can maintain their current pace of development.
  4. Ask the project manager to reassign two developers to the 'Testing' team to clear the backlog. given the information provided

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 92,240+ practice questions, 30,500+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials