Larkspur Health is using a Kanban system for its patient portal updates. The team reports that their Lead Time is 14 days, but their Cycle Time is only 2 days. Stakeholders are complaining about the slow delivery.

Where should the project manager focus the improvement efforts?

  1. Analyze the 'Ready' queue and the intake process to reduce waiting time before work begins.
  2. Submit a change request to move the project from an adaptive to a predictive lifecycle, while documenting the decision in the issue log.
  3. Implement pair programming to further reduce the Cycle Time from 2 days to 1 day.
  4. Direct the developers to work on more items simultaneously to increase the throughput.

Sign up free to see the explanation and track your rank →

More Project Management Professional adaptive practice

KomFi: Test Prep Made Easy

KomFi: Test Prep Made Easy — free adaptive practice for GMAT, GRE, SAT, ACT, National Real Estate Exam, Investment Banking, and finance with full explanations.

KomFi Academy is free GMAT prep and personalized GMAT help built as a training platform: 89,613+ practice questions, 30,000+ flashcards, on-demand video lectures, podcasts, and 4K slide decks. Flagship tracks: Free GMAT Prep, Free GMAT Resources, National Real Estate Exam Prep, Investment Banking Prep, Finance Prep, GRE, SAT, ACT, LSAT, MCAT, Financial Accounting, Private Equity, Private Credit, and Quantitative Finance.

Free GMAT Prep & Personalized GMAT Help

What's inside

Topics

View pricing · Read testimonials