Larkspur Health is using a Kanban system for its patient portal updates. The team reports that their Lead Time is 14 days, but their Cycle Time is only 2 days. Stakeholders are complaining about the slow delivery.
Where should the project manager focus the improvement efforts?
- Analyze the 'Ready' queue and the intake process to reduce waiting time before work begins.
- Submit a change request to move the project from an adaptive to a predictive lifecycle, while documenting the decision in the issue log.
- Implement pair programming to further reduce the Cycle Time from 2 days to 1 day.
- Direct the developers to work on more items simultaneously to increase the throughput.
Sign up free to see the explanation and track your rank →
More Project Management Professional adaptive practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started forming… — How should the project man
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… — What is the best way for th
- During a Trestle Ports retrospective, several team members e… — How should the Scrum Maste
- Who is correct?