Peakstone Rail is managing a track maintenance project using Kanban. The project manager wants to improve 'predictability' for stakeholders.

Which CFD signature should they optimize for?

  1. Eliminating all intermediate bands so only 'Arrival' and 'Done' are visible.
  2. Keeping the total thickness of the stack (Total WIP) at its maximum allowed limit.
  3. Maintaining parallel band edges with stable, non-diverging slopes over time.
  4. Ensuring the 'Done' line slope is as steep as possible, regardless of the 'Arrival' line.