hard · Project Management Professional Adaptive / Agile
Peakstone Rail is managing a track maintenance project using Kanban. The project manager wants to improve 'predictability' for stakeholders.
Which CFD signature should they optimize for?
- Eliminating all intermediate bands so only 'Arrival' and 'Done' are visible.
- Keeping the total thickness of the stack (Total WIP) at its maximum allowed limit.
- Maintaining parallel band edges with stable, non-diverging slopes over time.
- Ensuring the 'Done' line slope is as steep as possible, regardless of the 'Arrival' line.
Sign up free to see the explanation and track your rank →
More Project Management Professional Adaptive / Agile practice
- What is the most appropriate action for the project manager?
- What should the Scrum Master do first?
- What should the Scrum Master do next?
- Members of the Trestle Ports agile team have started… How should the project manager…
- What should the Scrum Master do first?
- A project manager at Kestrel Civic is leading a team new to… What is the best way for the…
- During a Trestle Ports retrospective, several team members… How should the Scrum Master…
- Who is correct?
All Adaptive / Agile questions · Project Management Professional study guide · Project Management Professional glossary · Project Management Professional flashcards