Stonehaven Transit is negotiating an agile contract with a new vendor. The project manager wants to limit the organization's financial risk while allowing for scope flexibility.

Which contract structure is best?

  1. A Cost Plus Fixed Fee (CPFF) contract with no ceiling.
  2. A Time and Materials (T&M) contract with no reporting requirements.
  3. Incremental delivery with defined exit points after each release.
  4. A standard Firm Fixed Price (FFP) contract for the entire backlog.