Dovetail Clinics is implementing an adaptive scheduling system. The team velocity is stable at 20 points per sprint. The Product Owner wants to maximize the economic value delivered in the first sprint.
Which features should be included?
- F1, F4, F2
- F2, F3, F1
- Escalate the sprint plan to the Clinical Director
- F1, F4 only